1. The excerpt from the ToR which has been made available does not contain a passage on the optional grounds for exclusion. Should it be assumed that the Contracting Authority in the documentation of the proceedings provided for the exclusion of the contractor under Article 109(1)(10) of the PPL Act?
Answer: YES, it should be assumed that the Contracting Authority in the documentation of the proceedings provided for the exclusion of the contractor under Article 109 (1) (10) of the PPL Act.
2. May the Employer's/Contractor's representatives act as professional proxies, i.e. be named and sign as e.g. Legal Adviser/Attorney Jan Kowalski?
Answer: Yes. They can.